Source: New Zealand Transport Agency
New resilience work recently got underway on State Highway 1 in Marlborough, south of Blenheim at Dashwood.
- The start date for the second stage of this work has now been brought forward to start on Monday, 17 February to help avoid the upcoming grape harvest, says NZ Transport Agency Waka Kotahi (NZTA).
During this time one lane of the highway will remain open under stop/go traffic management 24/7 and a 30 km/h temporary speed limit.
- Work is expected to continue until 9 April 2025, but NZTA is aiming to have an end to stop/go traffic management by early March.
The work involves raising the height of the road to minimise future flooding and complete drainage improvements.
Wayne Oldfield, Marlborough System Manager, says the 500-metre section of state highway between Awatere Valley Road and the Awatere Bridge is prone to flooding.
“Making these improvements and increasing the highway’s resilience will help keep the road open in bad weather, and ensure people, products, and places remain connected on this busy arterial route.”
“It means the transport network will be stronger and better prepared for any future disruption,” Mr Oldfield says.
The work on the three-lane section of the state highway will be carried out in stages.
Stage 1 will see the start of new drainage works alongside the highway. During Stage 2, one lane of the highway will remain open under a stop/go traffic management 24/7 and a 30 km/h temporary speed limit. For Stage 3, two lanes will be open under a 30 km/h temporary speed limit.
Keeping the road open while work is done is particularly important given the Marlborough grape harvest will soon be underway.
Mr Oldfield says the work is funded by the Crown Resilience Programme.
“The fund is about covering the cost of resilience improvements on the state highway network and minimising damage from future weather events.”
“Marlborough residents know only too well how big an impact floods can have. In previous years, heavy rainfall has resulted in the closure of this stretch of the highway. Investments like this can make a big difference,” Mr Oldfield says.
Other resilience works recently completed in Marlborough include State Highway 6 Rai Saddle and State Highway 63 at the Wash Bridge.
Works Schedule overall
Stage 1 – Early February to 9 April
- Drainage works undertaken in the swale alongside the highway.
- Northbound passing lane will be closed during the work activities.
Stage 2 – 17 February to early March (amended from our first notice of this work)
- Stop/Go temporary traffic management in place from 24/7 – No work on Sundays.
- A temporary speed limit of 30 km/h will be in place at the site 24/7.
- Expect delays of up to 10 minutes.
- This work is subject to weather and unforeseen circumstances.
Stage 3 – Early to late March
- State Highway 1 reopened to two lanes
- A temporary speed limit of 30 km/h will be in place at the site 24/7.
More Information
- The Crown Resilience Programme (previously the Transport Resilience Fund) is a $419 million investment package of resilience improvement activities that will reduce the impact of severe weather events on our national roading networks. This will ensure a more resilient and efficient network now and into the future. The total crown resilience programme comprises $279 million for activities on State Highways, and $140 million for activities on Local Roads.
- This seven-year programme aims to advance proactive resilience improvements on the roading network to minimise the future damage caused to New Zealand roads by weather events, which have been increasing in frequency and severity.
- Crown Resilience Programme