Roll on Summer! Northland’s state highway renewal season

0
2

Source: New Zealand Transport Agency

Road users can expect to see significant upgrades along Northland’s vital transport routes this summer, with contractors for NZ Transport Agency Waka Kotahi (NZTA) out renewing 204 lane kilometres* of state highway.

It’s the second year of the largest-ever investment in state highway maintenance for the region.

“Northland’s state highways are crucial for connecting communities, supporting local businesses, and keeping freight moving efficiently, which is why we’re investing $258.6 million for state highway maintenance and pothole prevention, and an additional $3.5 million for managing road subsidence, between 2024 – 2027,” says Regional Manager of Maintenance and Operations, Jacqui Hori-Hoult.

The 2025-2026 season (September – May) includes 25 lane kilometres of major road rebuilds, 8 lane kilometres of asphalt resurfacing and 171 lane kilometres of chipsealing.

There will be major works on State Highway 1 (SH1), State Highway 10 (SH10) and State Highway 12 (SH12), spanning the region from north of Woodhill and Warkworth to Te Reinga Wairua (Cape Reinga). 

“The region’s roads face unique challenges, including heavy rainfall and the demands of high-volume traffic. By renewing the network, we strengthen road pavements, improve surface durability, and enhance overall network resilience, so Northlanders can travel safely and reliably year-round,” Ms Hori-Hoult says.

NZTA schedules work during the spring and summer months to take advantage of warmer, drier weather which helps sealants set properly and last longer. It’s about ensuring a quality surface.

“This means road users will sometimes experience temporary full road closures to enable multiple teams to work at the same time. We appreciate roadworks are inconvenient, but doing the work this way is more efficient and minimises disruption in the long term,” Ms Hori-Hoult says.

Most work is undertaken at night or outside peak travel periods to reduce the impact on road users.  

The work is weather dependent and some dates may change.

Location

Type of work

Dates

Traffic Impact

SH1 Towai

Rebuild

Jul–Nov 2025 (12 weeks)

Day: stop/go, speed restrictions

SH10 Oromahoe

Rebuild

Oct–Nov 2025 (6 weeks)

Day/Night: stop/go, speed restrictions

SH1 Akerama

Rebuild

Oct–Dec 2025 (8 weeks)

Day: contraflow, speed restrictions

SH1 Whakapara (2 sites)

Rebuild

Nov 2025 (3 weeks)

Night: stop/go, speed restrictions

SH1 Brynderwyn Hills

Resurfacing

13–16 & 20–23 Nov 2025

(2x 4-day super weekends)

24/7 full closure, detours

SH1 S of Uretiti & Waipu

Resealing ×2

Nov 2025 (2 weeks) Dec 2025 (1 week)

Day/Night: stop/go, speed restrictions

SH12 Baylys Coast Rd, Dargaville

Rebuild

Nov–Dec 2025 (5 weeks)

Day: stop/go, speed restrictions, 24/hr traffic management

SH12 Dargaville (Blong/Galvin/Hodgson-Wallace)

Rebuilds ×3

Blong: Sep–Nov 2025

(6 weeks)

Galvin: Jan–Feb 2026

(5 weeks)

Hodgson–Wallace:

Mar–Apr 2026 (6 weeks)

Day: stop/go, speed restrictions, 24/hr management

SH12 Paparoa township

Rebuild

Jan–Mar 2026 (8 weeks)

Day: stop/go, speed restrictions

Further information, including maps, project updates, and weekly e-newsletters, is available via: