Crews will be resurfacing State Highway 44 Molesworth Street in New Plymouth from next Monday.

The overnight work is scheduled to begin Monday 20 January and is expected to take 10-12 nights to complete.

During the work, crews will be onsite between 7pm and 6am and the road will be under stop/go traffic management.

Delays of between 5 and 10 minutes can be expected.

Outside the overnight work hours, the road will be open with a 30 km/h speed limit in place.

Access to and from some sideroads adjacent to SH44 may be impacted temporarily while work is taking place.

NZ Transport Agency Waka Kotahi is advising road users to plan ahead during this work and take advantage of alternative routes.

NZTA appreciates the overnight closures will cause disruption and we’re confident that by doing the work overnight, the construction timeframe will be as short as possible.

This work is weather dependant.