A reminder that maintenance work will begin soon on a stretch of State Highway 2 just north of Waipawa.

The road rebuild will be carried out in stages from 13 January to the end of March. Crews will focus on a 500 metre stretch of SH2, between Tamumu Road and Victoria Street.

Work will initially be focussed on installing new kerbs and improving channels. This is a continuation of the kerb and channel work undertaken in this section earlier this year.

Once the kerbs and channels are completed, crews will start rebuilding the road surface. This will involve recycling the existing road materials with cement added to the pavement, to improve and extend the life of the road and improve the journey through this section.

“Our crews will be working days and some nights to speed up the works and complete the job as quickly as possible,” says NZ Transport Agency Waka Kotahi Regional Manager of Maintenance and Operations Rua Pani.

“There will be different traffic management set ups at different stages of the work which will be communicated before the works begin. We advise road users to please expect short delays through this worksite at times and to plan their journeys accordingly.”

“We know this work will be frustrating for road users and residents, and for local businesses and communities in the area. We also know Waipawa has already seen its fair share of disruption during earlier improvements on the main street and we are working with Central Hawkes’ Bay District Council (CHBDC) to minimise the impact these works will have on the community.”

“Ultimately, this work will improve the efficiency of travel for all road users, hopefully minimising disruptions in future,” says Ms Pani.