Source: New Zealand Transport Agency

Drivers travelling at the top of the South Island can expect lots of activity this summer as NZ Transport Agency Waka Kotahi invests in resurfacing and rebuilding the region’s highways.

Mark Owen, Regional Manager Lower North Island/Top of the South, says it is critical state highways are well-maintained to a reliable standard.

“This work is about ensuring everyone can use them efficiently, quickly, and safely.”

Mr Owen says our busy work programme is underway with one project almost complete.

“It means drivers will see more road crews and work sites when travelling over the next few months.”

“We will do as much work as possible between now and mid-December, which will mean less impact on holiday travel over the summer break,” Mr Owen says.

He says this year’s summer maintenance programme will renew just short of 150 lane kilometres on local state highways – slightly more than what was completed last season.

“This will see around 8,100 tonnes of asphalt and around 100 lane kilometres of chipseal laid by our crews across the Nelson, Tasman and Marlborough regions. The result will be safer, smoother journeys for motorists.”

Most of the work will be done during night closures to minimise disruption and reduce cost through less traffic management.

Work will also be done at several other smaller sites across the top of the South Island under stop/go traffic management. The public will receive further information before the projects begin.

Mr Owen says there’s more than just summer maintenance work to do.

“We have repair work on SH60 Tākaka Hill following a slip in July, proactive resilience projects underway on SH63 and about to begin on SH6 Rai Saddle in Marlborough, and ongoing work to repair the Marlborough Sounds roads.”

“There are also other ongoing safety improvement projects like the SH6 Tancred Crescent Roundabout at the Marlborough Airport,’ Mr Owen says.

He says with so much work planned, drivers need to check road conditions before they travel. 

“Planning ahead and knowing what’s happening on the network can save you time and hassles. Knowing when and where roadworks are happening means you can time your travel to avoid them or allow extra time for your trip.”

Mr Owen says allowing extra time is essential for people travelling between Christchurch to Picton, and between Blenheim and Nelson.”

“If you’re traveling to the ferry or for an appointment, we recommend allowing an extra 60 minutes travel time between Christchurch and Picton and an extra 30 minutes if you’re traveling between Nelson and Blenheim.”

Mr Owen acknowledges that roadworks occur more frequently during spring, summer, and early autumn and affect people’s travel – but there’s a good reason for it.

“To be effective and durable, road renewals and re-sealing must be done during the warmer, drier months. It can’t be done during winter when the weather is wet and cold.”

“Whenever you come to a worksite, remember that our road workers are doing their best to complete their work and keep you moving. Please be respectful and follow their advice and instructions,” Mr Owen says.

Summer Maintenance Schedule – Top of the South Island

Location

Month

Duration of work

Type of work

SH6 Gladstone Road, Richmond

In progress

2 weeks of night closures

Resurfacing

SH63 The Wash, Marlborough

In progress

8 weeks of daytime stop/go

Resilience

SH6 Rai Saddle, Marlborough

14 October – 22 November

24/7 stop/go

Resilience

SH60 Mariri Causeway, Motueka

19 October

1-day closure

Resurfacing

SH1 Weld Pass, Marlborough

20 – 23 October

4-night closures

Drainage

SH6 Canvastown, Marlborough

November

3 weeks of Stop/Go

Rebuilding

SH6 Tunnicliffe Bridge, Motupiko, Tasman

October/November

3 weeks of stop/go followed by 2 weeks of night closures

Rebuilding

SH60 Commercial Street, Golden Bay, Tasman

November

1 week of night closures

Resurfacing

SH60 Tākaka Hill, Tasman
NB: Other work at the underslip site on SH60 Tākaka Hill will also be carried out to repair the road to two lanes before Christmas

November

4 weeks including
3 weeks of night closures + 1 week of day closures)

Resurfacing (3 weeks)
Resealing (1 week)

SH6 Pelorus, Marlborough

December

4 weeks of stop/go

Rebuilding

SH1 Main Street roundabout, Blenheim 

January/February

1 week of night closures

Resurfacing

SH6 Annesbrook Drive, Tāhunanui, Nelson

January

1 week of night closures

Resurfacing

SH1 Grovetown, Marlborough

February

3 weeks including night closures and stop/go

Rebuilding

SH6 Whangamoa

February

2 to 3 weeks of night closures

Resurfacing, drainage, other general maintenance i.e. guardrails, signage

SH6 Havelock, Marlborough

February

1 week of night closures or stop/go at the same time as the SH6 Whangamoa night closure to maximise efficiency

Resurfacing

SH1 Weld Pass, Marlborough

February

2 weeks of night closures

Resurfacing and other general maintenance i.e guardrails, signage

SH1 South of Riverlands/Co-op Drain

February

2 weeks of stop/go

Rebuilding

SH1 South of Seddon/Taimate

February/March

3 weeks of stop/go

Rebuilding

Note: The works in the table above may change due to weather and other unforeseen circumstances.

Summer Maintenance Programme – additional information

  • Key holiday periods are kept free of roadworks to help ease the pressure on peak travel times. 
  • More information about our summer maintenance work can be found on our website
  • Further details about  planned National Land Transport Programme (NLTP) 2024-27 investment for the top of the South Island are also available online 