Source: New Zealand Transport Agency

Underslip repairs starting soon on State Highway 36, will require the highway to be fully closed during the day for 2 weeks between Mangorewa Gorge and Hamurana.

After heavy rain in 2023, an underslip developed approximately 500 metres south of the Mangorewa track carpark. Geotechnical investigations are complete, and repairs are due to start on 2 worksites from Monday 5 August. 

NZ Transport Agency Waka Kotahi (NZTA) advises work will take approximately 6 weeks to complete, weather permitting, and road users should plan ahead. 

The first 2 weeks of work require daytime closures Monday to Friday from 8am to 4pm between Pyes Pā roundabout and Hamurana. Access during this time will be for residents only. Outside of these hours, 1 lane will be closed with stop/go traffic lights in place.  

The following 4 weeks of work will require permanent stop/go traffic management. 

Contractors will be cutting into the bank to realign the road. This work requires a large amount of heavy machinery, and the daytime closures are required to keep the travelling public and workers safe. 

Following the initial 2-week closure, a further 2 slips will be repaired about 200m south of Te Waerenga Road. This will involve retaining and rehabilitating the existing road. During this work there will be permanent stop/go traffic management in place. 

Crews will be undertaking maintenance works in addition to the slip repairs, to make the most of the traffic management in place. 

During the full closure the detour for all vehicles travelling between Pyes Pā Road and Hamurana will be via SH29A, SH2 Tauranga Eastern Link Toll Road (or Te Puke Highway), continuing to SH33 through Paengaroa, then SH30 and SH30A through Rotorua, turning right onto SH5 and rejoining SH36 at Ngongotahā. 

NTZA appreciates road users’ understanding while this vital work to repair the highway is being completed. 