Source: New Zealand Transport Agency
Regular users of State Highway 2, Remutaka Hill, need to plan ahead for a pending road closure this coming weekend.
The route will be closed to allow contractors to do essential maintenance. It will be carried out over two nights – Sunday, 9 October and Monday, 10 October, and the road will be closed from 9pm to 4am.
These overnight closures will allow road resurfacing, mowing, slip, and drain clearing to be carried out.
The addition of the Monday night closure to the previously publicised schedule is needed because of the damage caused to the highway by recent severe weather. State Highway 2, Remutaka Hill, is a crucial transport link, and this work is essential for keeping the road up to standard and safe for road users.
These closures significantly reduce the number of daytime disruptions for road users. Road crews can also complete a large amount of work safely over a small number of closures because multiple crews can work across the hill at the same time without disrupting traffic.
Crossing information:
- We cannot offer crossings of the Remutaka Hill during the maintenance closures unless a traveller has special circumstances and has booked one of three time slots available:
- Hutt to Featherston 10.30 pm
- Featherston to Hutt 11.30 pm
- Hutt to Featherston 12.30 am
- The amount of work taking place makes unplanned crossings unsafe to manage – for both road crews and road users. Any travellers with special circumstances should contact customer@wta.nzta.govt.nz
Otherwise, we regret that travellers turning up without a booking will be turned away. - Road access will be available for emergency services.
- More information about the closures can be found at www.nzta.govt.nz/remutaka or email remutaka@nzta.govt.nz
Waka Kotahi understands the closure may inconvenience some road users and thanks them for their patience and understanding as crews carry out this essential work.
Regular users of this route are encouraged to stay up-to-date on upcoming closures. While these dates are fixed, bad weather may cause work to be cancelled. A full list of planned closures is in the table below:
Scheduled Remutaka Hill State Highway 2 closures 2022–2023
Nights | Start 9pm | Finish 4am |
---|---|---|
2 | Sunday 9 October 2022 | *Tuesday 11 October 2022 |
5 | Sunday 6 November 2022 | Friday 11 November 2022 |
1 | Sunday 8 January 2023 | Monday 9 January 2023 |
5 | Sunday 26 February 2023 | Friday 3 March 2023 |
1 | Sunday 9 April 2023 | Monday 10 April 2023 |
*10 |
Sunday 14 May 2023 *Sunday 21 May 2023 |
Friday 19 May 2023 Friday 26 May 2023 |
1 | Sunday 11 June 2023 | Monday 12 June 2023 |
* Additional night required for essential maintenance and slip clearing.
* Contingency – additional block of closures included in case a special resilience project is required.
Find out more about planned roadworks in the Wellington/Wairarapa region(external link)